Northfield Road, Liverpool

Complete Demolition were appointed to deliver emergency demolition works on Northfield Road, Bootle for Carroll Build.  There was severe damage to the walls of the extension and the main building which had been caused by subsidence due to drainage issues.

The demolition team commenced with the opening of the timber floor to determine the structure/sub-base of the building.  When this was deemed fit for purpose the team working from a tower scaffold erected props.  Upon completion, this was signed-off by the temporary works co-ordinator. Experienced operatives then began with the removal of the extension roof, when finished the scaffold shoring was dismantled and the historic propping removed.  Works then moved onto the hand demolition of the extension.  When all defective brickwork was repaired the steel beams were securely put back into position.  Finishing works included the openings being blocked-up using concrete bricks.