Lodge Lane, Liverpool

Complete Demolition were appointed as Principal Contractor to carry out the asbestos removal and full demolition on a Former School Hall and Changing Rooms on Lodge Lane, Liverpool.

The works comprised of scaffold erection, asbestos removal, clearing out, mechanical demolition, crushing of materials and site finishing works. The works were undertaken to facilitate the construction of a new football pitch.

The buildings were fully scaffolded prior to the asbestos removal which was undertaken under fully controlled conditions. The buildings were then mechanically demolished by a 30 tonne demolition excavator fitted with a specialist attachment which sorted the waste during the demolition process.  Through mutual agreement it was decided that the concrete aggregate would be crushed onsite to be used in the construction phase of works. Site finishing works included tree removal, stump grinding and grass flailing.

98% of demolition waste was diverted from landfill.